Forward Deployed Engineering in Practice · Capstone Case Studies

Capstone: Postmortem — The Pilot That Stalled

A 10-week pilot ended without a production decision. Reconstruct what went wrong and how a forward deployed engineer could have changed the outcome.

Create a free account to save this page, take notes and track your progress. Sign in

Scenario

Example customer: a logistics company piloted a vendor's AI route-exception assistant with one regional operations team. The pilot was planned for 10 weeks. In week 12 the customer's COO declined to proceed: "Nice technology, unclear value."

Evidence

  • Kickoff deck listed goals as "improve operations with AI"; no metric or baseline was recorded.
  • Security review started in week 4 and finished in week 9; real data arrived in week 9.
  • Weeks 1-8 used synthetic data; demos impressed the sponsor's team but operators found the scenarios unrealistic.
  • The FDE built 19 requested features, including four dashboards; the core exception workflow shipped in week 10.
  • Weekly status emails listed completed tasks; no risks were raised before week 8.
  • The sponsor (a regional director) changed roles in week 7; nobody re-engaged the COO.
  • Three other customers had asked the vendor's product team for the same data connector the FDE built by hand.

Deliverables

  1. The main reasons the pilot stalled.
  2. What should have happened in the first two weeks.
  3. How to recover the account now, if possible.
  4. What the vendor should change for future pilots.

Draft each deliverable before revealing the model answer and rubric.

Further reading: Shape Up · NIST AI Risk Management Framework

Deliverables

Why did the pilot stall?

Model answer

  • No measurable success criteria or baseline, so value couldn't be demonstrated.
  • Security review started late and sat on the critical path; real data arrived in week 9.
  • Effort spread across 19 requests instead of the core workflow.
  • Status reporting hid risks; the sponsor change wasn't managed and the executive decision-maker was never engaged.

Rubric

Full marks: identifies missing success criteria, late critical-path dependency, scope dilution and stakeholder management failures.

What should have happened in the first two weeks?

Model answer

Shadow operators to find the top exception types and their cost; agree one or two metrics with a baseline (for example, time to resolve route exceptions, missed delivery windows); write a one-page scope with out-of-scope items; submit security and data-access requests on day one; map stakeholders including the COO as decision-maker; set a weekly status with risks and asks; plan an evaluation using real historical exceptions.

Rubric

Full marks: concrete discovery, metrics with baseline, early approvals, stakeholder mapping and risk-based reporting.

How could the account be recovered?

Model answer

Propose a short, focused extension (4 weeks) with explicit success criteria and the baseline measured from historical data; run the core workflow with real data for the original team; meet the new sponsor and the COO with a one-page value case and the measurement plan; drop non-core features from scope; agree the production decision criteria upfront.

Rubric

Full marks: specific, time-boxed recovery tied to measurable value and the actual decision-maker.

What should the vendor change for future pilots?

Model answer

A pilot playbook: success criteria and baseline required at kickoff; standard security package and day-one access requests; real-data milestone by week 3; triage process for requests; weekly risk-based status; executive check-ins at kickoff, midpoint and end; FDE field feedback flowing to product (the connector three customers needed should become a product feature).

Rubric

Full marks: systemic changes across process, product feedback and executive engagement, not just individual effort.