Forward Deployed Engineering Tutorial · Discovery and Scoping · Lesson 6 of 24

Deployment Plans and Milestones

Plan a customer deployment: milestones, dependencies, critical path, risks, and a status update format customers trust.

Create a free account to save this page, take notes and track your progress. Sign in

Milestones tied to outcomes

Milestone Done when
Access Credentials, network access and test data available
First data flowing Real data from source systems arrives, validated
Pilot 3-5 real users use the workflow on real cases
Production Monitoring, support, runbook and handover in place; success criteria met
Expansion Next team or workflow scoped

Dependencies and the critical path

Customer-side dependencies (security review, firewall changes, API keys, data owner approval) usually take longer than engineering. Start them on day one and track them visibly.

Find the critical pathTry it yourself
from graphlib import TopologicalSorter

tasks = {  # name: (days, depends on)
    "security review": (15, []), "API credentials": (5, []), "firewall allow-list": (10, ["security review"]),
    "build connector": (8, ["API credentials"]), "data validation": (4, ["build connector", "firewall allow-list"]),
    "pilot": (10, ["data validation"]),
}
finish = {}
for t in TopologicalSorter({k: set(v[1]) for k, v in tasks.items()}).static_order():
    days, deps = tasks[t]
    finish[t] = max((finish[d] for d in deps), default=0) + days
path, t = [], "pilot"
while t:
    path.append(t)
    deps = tasks[t][1]
    t = max(deps, key=lambda d: finish[d]) if deps else None
print("pilot can start using real data on day", finish["data validation"])
print("critical path:", " -> ".join(reversed(path)), f"({finish['pilot']} days)")

Output

pilot can start using real data on day 29
critical path: security review -> firewall allow-list -> data validation -> pilot (39 days)

Status updates

Weekly, short, the same format every time: progress against milestones, what's next, risks and asks (what you need from whom by when), and decisions needed. Bad news early, with options.

Test yourself

What usually sits on the critical path of an enterprise deployment?

  1. Writing the code
  2. Customer-side approvals like security reviews and network access
  3. Choosing colours
  4. Unit tests
Show answer

Answer: Customer-side approvals like security reviews and network access

Start approvals on day one; they often take longer than building.